By Kent Barker

Plans to complete – or even start work on completing – the Queensway Gateway to the A21 appear to have been put indefinitely on hold. Six years ago the scheme obtained planning consent and the western section of the link was completed in 2019. Since then it has languished as a ‘road to nowhere’.

The hot weather, which this summer has attracted large numbers of tourists, has also led to record queues of motorists trying to get into Hastings under the Ridgeway viaduct on the A21 near the Dunelm business park.  The ‘Gateway’ access to the Bexhill Link Road was designed to ease this congestion, initially with a roundabout. However when the lead developer for the scheme, Sea Change Sussex, was unable to obtain the land needed for the roundabout, they proposed an interim modified junction by Bartlett’s car dealership (see diagram).

Work on this has been constantly delayed. At the end of last year Sea Change promised an eight-week programme of works to start ‘as soon as possible’. This week Sea Change told the Hastings Independent: “We are still waiting for permission to do this from the highway authorities.” One of those authorities is East Sussex County Council, which has already given Sea Change at least £15 million pounds of grant funding. The leader of ESCC Keith Glazier said earlier this summer: “I recognise the frustration that everyone feels in relation to this project. I can assure you that I share that frustration too.” 

Part of the problem seems to be the labyrinthine structure of the organisations that were set up to aid development of the so-called ‘Bexhill Growth Corridor’. At the top of the pyramid is SELEP – the South East Local Enterprise Partnership.  SELAP covers East Sussex, Essex, Kent, Medway, Southend and Thurrock. It is one of 31 LEPs established by the government in 2011 to “identify and support local strategic growth priorities… putting business in the driving seat and empowering the private sector to determine its own priorities”. The tier below SELAP is East Sussex County Council which has responsibility for highways. Together they commissioned Sea Change Sussex – a not-for-profit ‘economic development company for the county’ to deliver the growth corridor including the gateway route to the Bexhill Link Road.

- Advertisement -
St Michaels Hospice Run Advert

So far so good. But the ESCC along with Hastings Borough and Rother District councils are also directly involved in Sea Change – indeed together they ‘own’ 19% of the company and each has a director on the board. Or at least they did until both Hastings’ and Rother’s representative resigned earlier this year. HBC’s Councillor Paul Barnett announced his departure at the end of February, remaining tight lipped about the reasons “due to reviews now ongoing into the company with regard to funding received by the company for its projects within our local enterprise partnership.” 

Rother District councillor Kevin Dixon was rather more forthcoming: “Having been on the Board for over two years I have felt that the reputational damage to myself and to the Council of being associated with Sea Change is just too great,” he told a council meeting in February. “The reality is that Sea Change is in constant conflict with all three authorities – and the regeneration aims and objectives of all parties are being severely compromised as a result,” he said.

Certainly, ESCC is unhappy about Sea Change even if it retains its seat on the board. Last November it confirmed that £3.5m allocated to the controversial North Queensway business park project would be withdrawn, as “terms for the funding had not been met” (see HIP 26.11.2021 and issues passim). It is the County Council that is ultimately responsible for the delivery of the Queensway Gateway project, however they did not respond to HIP’s request for further information or comment in time for publication.  

In the meantime, individual councillors are clearly becoming frustrated at the ongoing delays and the reluctance of Sea Change to address them. At Hastings Borough Council’s Overview and Scrutiny Committee meeting last month Cllr Peter Pragnell said it was  imperative “we get Sea Change in front of us.” The committee chair, Cllr Andy Patmore, agreed there were a lot of unanswered questions that had been given to the company and, in a note of frustration, declared it was “essential that we could somehow have somebody who was responsible for something to come and answer (those) questions.” Sea Change itself still maintains it is not their fault: “We’ve delivered the vast majority of the road project, with only minor construction work needed to complete the link through to the A21 via a traffic signal junction. We’re frustrated by the ongoing delays and keen to get the road open to through traffic as soon as possible.”

Just how soon that might be is a clearly moot point. If Sea Change is refusing to discuss the situation with the HBC and is in conflict with its other partners, the prognosis does not look promising. As Rother’s Cllr Kevin Dixon says: “The lack of progress on key projects and the constant disagreements with the three local authorities mean that, in my opinion, the Company is not achieving its aims.” Perhaps removing its responsibility for construction of the Gateway might be the only way to complete the project. But given the complexity of the company’s ownership, that might take a very long time to achieve. In the meantime the frustration continues for motorists stuck in apparently unending traffic jams. 


We hope you have enjoyed reading this article. The future of our volunteer led, non-profit publication would be far more secure with the aid of a small donation. You can also support local journalism by becoming a friend of HIP. It only takes a minute and we would be very grateful.

https://www.hastingsindependentpress.co.uk/wp-content/uploads/2022/08/diverted-traffic-road-block.jpghttps://www.hastingsindependentpress.co.uk/wp-content/uploads/2022/08/diverted-traffic-road-block-150x150.jpgHIPNewsBexhill Growth Corridor,Kent Barker,Queensway Gateway,Sea ChangeBy Kent Barker Plans to complete – or even start work on completing – the Queensway Gateway to the A21 appear to have been put indefinitely on hold. Six years ago the scheme obtained planning consent and the western section of the link was completed in 2019. Since then it...The Hastings & St Leonards non-profit community newspaper